Selkirk Copper completes Minto Phase 2 drilling in Yukon
Selkirk Copper Mines (TSXV: SCMI; US-OTC: SKRKF) has finished a second phase of drilling at the former Minto copper-gold-silver mine in Yukon, with 54,579 metres in 223 holes that are set to feed an updated resource estimate planned for March and a feasibility study on restarting the mine.
Infill drilling at Minto North returned 19.5 metres grading 1.27% copper, 1.49 grams gold and 5.6 grams silver per tonne from 212.1 metres downhole in hole 26SCM241, including 4.9 metres at 2.45% copper, 4.36 grams gold and 11.1 grams silver, the company said on Monday. At Area 118, hole 26SCM248, a 75-metre step-out from earlier drilling, cut 5.2 metres at 2.68% copper, 0.88 gram gold and 13.5 grams silver from 248.8 metres, beyond the limits of the previous resource estimate.
Hole 26SCM241 tested a 70-metre gap in the 202 Lens and hit mineralization at the expected elevation but with higher grade and thickness than earlier holes, Selkirk said. The 301 Lens tested by 26SCM248 was found in the first phase of drilling and lies within 150 metres of the existing underground decline.
"Importantly, this work has also led to a stepwise increase in our team's knowledge of the geology, how to explore for, and how to discover new zones of mineralization on the property," M. Colin Joudrie, Selkirk's president and chief executive, said in the company's statement.
Not yet counted
At Minto Main, infill hole 26SCM240 returned 10.2 metres at 1.35% copper, 0.64 gram gold and 9.3 grams silver from 341.3 metres, including 3.3 metres at 3.44% copper, 1.80 grams gold and 25.5 grams silver. At Copper Keel, 26SCM254 cut 53 metres at 0.68% copper, 0.23 gram gold and 1.9 grams silver from 94 metres, including 9 metres at 1.52% copper, 0.61 gram gold and 3.5 grams silver.
True widths are estimated at 80% to 90% of core lengths. The results are from holes drilled in June and July. Assays have been reported for 79 of the 223 holes, and with laboratory turnaround at about eight weeks, more are due through the winter.
The second phase was planned at 50,000 metres. None of it is in the current mineral resource or the preliminary economic assessment, which rest on the first phase of about 52,300 metres. Together the two phases total 106,879 metres over 14 months, which Selkirk says is 29% more than all drilling at Minto in the six decades before.
Restart plan
The September study outlined a 13-year restart of open-pit and underground mining feeding the existing 4,100-tonne-a-day plant. At $5.00 a pound copper, $3,600 an ounce gold and $50 an ounce silver, it put the after-tax net present value at a 7% discount rate at C$494 million ($346 million), with a 47.8% internal rate of return and a payback of 1.9 years from first production. Initial capital was estimated at $186 million. Payable metal in concentrate over the mine life totals about 377 million lb. copper, 225,000 oz. gold and 1.39 million oz. silver.
The study draws on Measured and Indicated resources of 47.8 million tonnes at 0.89% copper, 0.34 gram gold and 3.2 grams silver, for 940 million lb. copper, 530,000 oz. gold and 4.97 million oz. silver, plus Inferred resources of 16.9 million tonnes at 0.76% copper, 0.26 gram gold and 2.7 grams silver. It includes Inferred resources, which are too speculative geologically to be categorized as reserves, and there is no certainty its projections will be realized.
Minto produced copper concentrate as recently as May 2023. The Selkirk First Nation, based in Pelly Crossing, holds a controlling interest in the company through a wholly owned subsidiary.
Selkirk began a feasibility study at the start of November and plans to submit amended permit applications to the Yukon Environmental and Socio-economic Assessment Board in December. It has said Minto could produce its first concentrate in the second half of 2028.