AngloGold's $2.5-billion Quebradona plan faces permit wall
AngloGold Ashanti (NYSE: AU; JSE: ANG) has put a projected $2.5 billion on its Quebradona copper project in Colombia, conditional on an environmental licence that a law firm says cannot be issued while a government reserve over the area is in force, in principle until mid-2028.
Quebradona president Mateo Restrepo Villegas and Stewart Bailey, AngloGold's global vice-president of corporate affairs, gave the figure on Tuesday in New York, the company's Colombian unit said. Bailey said the project would bring exports of about $1.5 billion a year from 80,000 tonnes of production, conditional on environmental permits. In an Oct. 21 note, law firm Pérez-Llorca cited a company export estimate of about $1 billion a year.
Colombian Vice President José Manuel Restrepo Abondano, who attended the announcement, wrote on social media, according to the company, that the government trusts that, "once the environmental authorizations are obtained, this project will advance toward the start of its works in 2028" (translated from Spanish).
The underground mine is planned for Jericó, in the southwest of Antioquia department.
Reserve rules
Resolution 0855, signed by the Ministry of Environment and Sustainable Development on June 20, 2025, declared a temporary renewable natural resources reserve in six municipalities in southwestern Antioquia, including Jericó. The reserve covers more than 37,000 hectares, according to the ministry.
While it is in force, mining and environmental authorities may not grant new mining concessions or new environmental permits or licences for mineral exploration or exploitation, the resolution says. Projects that already hold a mining title, a technical mining instrument and an environmental instrument are not affected. The reserve runs for three years from the resolution's publication in the Diario Oficial, the official gazette, and can be extended by up to two years.
Pérez-Llorca said in its note that AngloGold can keep its mining title and file a new environmental impact study, but that the National Environmental Licensing Authority (ANLA) could not issue the licence while the reserve remains in force: in principle until mid-2028, or until 2030 if it is extended.
The law firm said AngloGold filed a suit seeking to annul the resolution in December 2025 that is still pending admission, and that the company recognized a $98-million loss on its investment in the project, covering exploration and evaluation costs.
ANLA archived an earlier licence application for the project in October 2021, finding the information submitted insufficient to rule on the project's viability, according to Pérez-Llorca. The firm notes that archiving the application was not a rejection on the merits and left the door open to a new study.
Álvaro Pico, AngloGold's director of sustainability and corporate affairs, told Colombian business newspaper Portafolio in September that the company was preparing its environmental impact study and expected a four-year construction phase starting in 2028 if the process went as planned, with copper exports beginning in 2032. Portafolio reported that the company estimates a resource of five million tonnes of copper.
AngloGold plans to submit its environmental licence application at the end of 2027, Pico said.